M-Block, Pitam Pura Size – 250 sq. yards
M-Block, Pitam Pura
- 250 sq. yards
- Stilt + 4 Floors
- 3BHK+ Longue
- Construction Start: April , 2016
- Completion: June , 2017
Project Description
This project is located in the Guru Harkishan Nagar locality of Paschim Vihar. It is built on a 250 sq. yards plot and has Stilt + 4 floors. Each floor follows a 3BHK configuration. This is Prithu’s first project as Builders in Paschim Vihar.
There are many Builders in Paschim Vihar but very few provide parking facilities in the stilt area. The stilt of this home can easily accommodate 8 cars. Each floor has 2 reserved parking spots which are independent from the other floors i.e. no interference from the neighbours if they want to park or take their car out.
The project is approximately 1.5 Kms from the nearest metro station of Peera Garhi.
Completed Project Pictures
- Living Room
- Bedroom
- Bathroom
- Kitchen
- Lobby
- Formal Drawing
- Elevation
Construction Pictures
December , 2017
Overview of the stilt area. On the left, underground water tank is being made.
November , 2017
Plastic cover is applied to the neighbouring wall to protect it from various construction procedures.
September , 2018
Plaster work complete on all the floors. Floor polishing in progress.
August , 2018
False ceiling work complete on all floors.
July , 2018
Wall tiles being installed in the bathrooms.
April , 2018
Provisioning for Air Conditioners being done on all the four floors. All the wall chasing is done through specialized machines to get clean grooves.
March , 2018
Space has been left beforehand for easy installation of skirting tiles. This method results in a better flooring finish.
February , 2018
Construction of Mumty in progress.
January , 2018
Pipes have been provided at the top of each underground tank so that overflowing water can be collected separately in a different tank, preventing spillage on the floor.
December , 2017
Overview of the stilt area. On the left, underground water tank is being made.
November , 2017
Plastic cover is applied to the neighbouring wall to protect it from various construction procedures.
September , 2018
Plaster work complete on all the floors. Floor polishing in progress.
August , 2018
False ceiling work complete on all floors.
July , 2018
Wall tiles being installed in the bathrooms.
April , 2018
Provisioning for Air Conditioners being done on all the four floors. All the wall chasing is done through specialized machines to get clean grooves.
March , 2018
Space has been left beforehand for easy installation of skirting tiles. This method results in a better flooring finish.
February , 2018
Construction of Mumty in progress.
January , 2018
Pipes have been provided at the top of each underground tank so that overflowing water can be collected separately in a different tank, preventing spillage on the floor.
December , 2017
Overview of the stilt area. On the left, underground water tank is being made.
November , 2017
Plastic cover is applied to the neighbouring wall to protect it from various construction procedures.